Design & Built of SWCC’s Al Jubail Desalination Plant 2nd Pass RO unit

Scope of work:

  • EPC (including basic and detailed design), installation and commissioning of a 2nd pass RO unit with capacity, 83,000 m3/d.
  • The purpose of the project was to minimize the Chloride & Boron concentrations for the final water product.

Key challenges:

  • Connecting the 2nd pass unit with the 1st pass unit while the plant was operational.
  • Inconsistent characteristics of effluent water.
  • Complexities in connecting to the Distributed Control system of the existing plant.

Key information:

  • Project Duration:  2016 – 2018 Project

Qulwa & Al-Makhwah Dam Water Treatment Plant

  • Project Name:Dam Water Treatment Plant
  • Capacity:  2 X 20,000 m3/day
  • Location:  Al Baha, Saudi Arabia
  • Purpose:  Treat Dam Water Using Ceramic Filters
  • Project Duration:  24 Months
  • Completion Date:  2024
  • Client:  National Water Company

Dammam 2nd Industrial City Drinking Water Treatment Plant

  • Project Name:Drinking Water Treatment Plant
  • Capacity:  15,000 m3/day
  • Location:  Dammam, Saudi Arabia
  • Purpose:  Treat Brackish Well Water using Reverse Osmosis Technology
  • Project Duration:  24 Months
  • Completion Date:  2016
  • O&M:  12 Months
  • Client:  Saudi Industrial Property Authority (Modon)

Buwaib & Salboukh Brackish Water Treatment Plant 

  • Capacity:120,000 m3/day
  • Location:  Riyadh, Saudi Arabia
  • Purpose:  Treat Brackish Well Water using Reverse Osmosis Technology
  • Project Duration: 24 Months
  • Completion Date:  2009
  • Client:  General Directorate of Water in Central Region, Ministry of Water