Water Desalination Projects
Design & Built of SWCC’s Al Jubail Desalination Plant 2nd Pass RO unit
Scope of work:
- EPC (including basic and detailed design), installation and commissioning of a 2nd pass RO unit with capacity, 83,000 m3/d.
- The purpose of the project was to minimize the Chloride & Boron concentrations for the final water product.
Key challenges:
- Connecting the 2nd pass unit with the 1st pass unit while the plant was.
- Operational Inconsistent characteristics of effluent water.
- Complexities in connecting to the Distributed Control system of the existing plant
Key information:
- Project Duration: 2016 – 2018 Project
- Value: SAR 46.5m
Qulwa & AlMekhwat Dam Water Treatment Plant
- Project Name: Dam Water Treatment Plant
- Capacity: 2 X 20,000 m3/day
- Location: Al Baha, Saudi Arabia.
- Purpose: Treat Dam Water Using Ceramic Filters
- Project Duration: 24 Months
- Completion Date: 2024
- Project Value: 64 Million Saudi Riyals.
- Client: National Water Company
Al Dammam 2nd Industrial City Drinking Water Treatment Plant
- Capacity: 150,000 m3/day
- Location: Jizan, Saudi Arabia.
- Client: Saline Water Conversion Corporation.
- Starting Year: July, 2019
- Completion Date: Augst, 2023
- Project Duration: 36 Months.
- Project Value: 45.8 Million Saudi Riyals
Al Buwaib & Salbokh Brackish Water Treatment Plant
- Capacity: 50,000 m3/day (Operation & Maintenance)
- Location: Buraidah, Saudi Arabia.
- Client: Ministry of Water & Electricity.
- Starting Year: March, 2017
- Project Duration: 60 Months.
- Completion Date: In Progress
- Project Value: 48 Million Saudi Riyals.